ADCO South is about 80 percent completed with the Bluffside roof replacement project. The remaining pending buildings on Bluffside are 20331 and 20301. ADCO South projects these two remaining roofs will completed by the end of 2023 weather permitting and in the new year they will start the Cape Coral buildings/roofs.